Snyder
& Associates Engineering contacted the Miller the Driller regarding jacking
in a square concrete tunnel for a bike trail. Miller had previous experience
with both square and round tunnels including completing a 122” OD steel tunnel
in East Peoria Illinois under railroad tracks for a bike trail.
After
looking at the sight, only four miles from the Miller shop, it was determined
that a square tunnel would not be a good solution. The Union Pacific
Railroad tracks were built on a levee. Levees are usually built on or
with fill materials, which can hinder a normal trenchless operation.
Because the north side of the levee (exit side) was very steep, there was nothing
there for a backstop to support any jacking or resist jacking loads that would
be applied. When
jacking square boxes under railroad tracks there is usually a large surface
area of the box to contend with. The tracks tend to move or shift with
the bore as it advances. Pipe ramming as well as the arch of the casing
has a much different forward motion, which allows the casing to be advanced
without movement of the tracks. Also needed was the ability to handle
the old railroad ties and tree stumps that were under the tracks. Permalok
steel casing was selected and installed. The 147" OD steel casing
with a 1.5" wall thickness was fabricated in 20' lengths. In a typical
weld in place operation, one 147” joint would normally take a week to weld and
x-ray. The time to make up a Permalok joint was less than one hour for
each joint. The snap together joint makes up water tight, without an
external or internal bell. The
project took 14 days from pit excavation to finish. Installation of the
Permalok pipe took only four of those days.
|