The Problem:
Install 4,200 feet of steel conduit under the Pacific Ocean on a curved
bore path with a limited work space, which made it impossible
to string out the conduit line ahead of time. In addition,
the inside surface of the pipe could not have any burrs or rough
edges that might snag, catch or cut the cables being installed
inside the conduit.
The Solution:
By using the new Permalok Type HDD connection, the contractor was
able to install 30' long sections of the conduit from the shore
side of the installation and complete the entire 4,200 foot run
of conduit in less than two days. Because the new HDD connection
provides a smooth interior surface with no slag or protrusions
common to welded joints, there was no concern of damage to the
cables.
The Permalok HDD technology allowed the flexibility to follow the
curved bore path and the pull-apart strength to resist any pull
back forces applied to the conduit. |